The project delivers 9 no. significant bridge and culvert structures across G2S North for HS2. The site is situated in Brampton.

140 Weeks
Duration
EKFB
Main Contractor
HS2
Client

Project Details

These have a included a variety of construction methods with large Viaducts, River Bridges, top-down structures, steel composite bridges, and PCC Integral Bridges with PCC shells used for Pier construction.

Management of all lifting including heavy lifts for Bridge beam installation has been a requirement of the project. Sian/CCS have undertaken the design, coordination and management of access across the site.

The project has required us to manage the coordination of reinforcement and concrete deliveries, setting out and planning of the works. We have undertaken the design, delivery and management of all temporary works.